Project Description

Client: Kallfass GmbH

Part 1: Fabrication and Installation of steel sub-structure.
Part 2: Installation of all plant and equipment for 6000m2 Grading and Finishing Line

Project Description

Kallfass GmbH were the main nominated mechanical supplier for this project. Being based in Germany it made economic sense for Kallfass to sub—contract the complete fabrication and installation of the project.

Kenneally Steel were awarded the contract with an estimated project duration of 12 months. This included responsibility for design, fabrication drawings, steel fabrication, painting, site installation and plant installation.

Kenneally Steel worked with Kallfass’ project engineer who was on site at all times on the design and fabrication of all structural steel. This work was carried out in a phased programme to allow machine installation to be carried out simultaneously with structural steel installation. As the project included the installation of two lines in one building, the second line was installed after the first line had commenced production.

To achieve this two crews were provided by Kenneally Steel – one focussed on Structural Steel and the other was dedicated to Plant Installation. Kenneally Steel provided all crane hire, teleporter and MEWPs for the project.

As the site had only one access point, all equipment had to be skated or rigged into position. This was carried out by our Banksman and Riggers which included multiple lifts for each machine section to be positioned in its final position.

This work was performed in 2013/2014 and was completed on time and on budget.

Client References available on request.

Key Details

  • Moving Wide Loads

  • Rigging & lifting awkward loads

  • Live Plant/ Production

  • International Customer